Gas infrastructure indicators

Indicator system, dashboards and reporting over the Córdoba gas network, prepared to IDB / IFC standards.

Period
2016 — 2023
Role
Business Analyst · Data Analyst
Power BIDAXSQLPower QueryETL
Placeholder for a photo of the route or the control room
Network
12,000 km

pipelines and branch lines

Stations
150

pressure regulating

Connections
500

industrial

Standard
IDB / IFC

multilateral reporting

The context

Seven years in public gas infrastructure in Córdoba. Other people built the works —that side is in End-to-end works management—; my job was knowing the state of everything and making it reportable to the organisations financing it, under their standards.

The network takes in trunk pipelines, distribution branch lines, pressure regulating stations and industrial connections. Every asset has its own cycle: it gets designed, tendered, built, commissioned, operated.

Gas network schematic: one head station, 12,000 km of trunk line, 150 pressure regulating stations and 500 industrial connections.Head stationTrunk line12,000 kmReg. stations150Industrial500Gas network schematic: one head station, 12,000 km of trunk line, 150 pressure regulating stations and 500 industrial connections.Head stationTrunk line12,000 kmReg. stations150Industrial500
Schematic — not the actual route

The problem

The data existed, but split across inspection, administration and operations — each area with its own cut-off dates and its own definition of progress.

When two areas reported different progress for the same job, it was almost never a data-entry error. It was that each one understood “progress” differently. That observation set up everything else: the problem was not about tools.

What I built

Outcome

The monthly report to the financing organisations went from 10 working days to 2. Not because assembling it was automated —though it was— but because with a single definition of progress there was no longer a reconciliation round between departments before anyone could write the first line.

That changed the question in the monthly meeting: from “which of these two numbers is the right one?” to “why did this job slip?”. The second one is the only one you can decide anything from.


⚠ Before publishing: confidentiality

The network’s operational data belongs to your employer, not to you, and this repository is public: whatever you push stays in the git history even if you delete it later.

What is yours is the method — the model, the indicator definitions, the reporting architecture.

Gallery

swipe to see all 2 →

Placeholder for a screenshot of the progress dashboard
Physical and financial progress dashboard — screenshot with synthetic data still pending
Placeholder for the data model diagram
Data model of the network — diagram still pending